There was a lot of progress on the garage this week. We got the trenches dug for the footings. Then the mason came in and laid out the forms for the footings. We then had the building inspector in to inspect the footings. The next day we had the concrete truck in and poured the footings. Now that the footings are poured we are all set for the mason to start laying up the foundation on Monday.
Digging footings
Footing forms ready for inspection
Poured footings ready for the foundation