There has been a lot of progress in the last week and a half. The mason has finished the foundation. We installed our footing drains and we have run all of our lines out to the building and then back fill everything. With the extra fill we were able to level out our parking area and make it bigger, as well as level off and re-grade our front yard. We also got half of our order of board and batten siding. The framing lumber will be delivered tomorrow.
Finished foundation
Trenching out for the footing drains
Everything backfilled
Half the order of siding
The front yard leveled and graded